Illustration by Adriana Heldiz for Voice of San Diego

An audit of San Diego’s contract with its monopoly power company shows longstanding problems over burying power lines continue to bog down the relationship. 

As part of SDG&E’s new 20-year contract with the city, in which San Diego placed new demands on their energy grid builder, the company agreed to be audited every two years. Crowe LLP Risk Consulting’s draft investigative report says that while SDG&E is mostly in compliance, the company and the city need to work on their communication skills as costs for burying powerlines are getting out of hand. 

Crowe found that SDG&E’s final bill to the city for at least one project was 81 percent higher than the company’s initial estimate to do the work. The initial estimate for the project, named Navajo Block 7T, was supposed to cost about $24.5 million. But months later the company came back and said it’d cost $44.3 million. That’s because the company didn’t include its “overhead costs” in the initial estimate, the consultants wrote.  

What are these overhead costs? That’s unclear and not explained in the report. Crowe’s consultants did not respond to multiple requests for comment.  

Why are we talking about this? Communities want to bury power lines underground for a multitude of reasons. If powerlines are underground, they won’t be damaged by storms, fall on trees and potentially spark fires and power outages. Some residents just don’t like the look of cables hanging high in the air over sidewalks. In any event, anyone who pays a power bill in the city of San Diego also pays to bury existing power lines underground. The city charges SDG&E the fee, and the utility company charges its customers.  

But the process is taking a lot longer than the city would like. Since 1970, 400 miles of overhead lines have been placed underground. But there’s still 1,000 miles left to do if the city is to reach the goal of undergrounding every residential wire. The rising costs of the projects are partly to blame for the slow pace, the consultants wrote. 

“SDG&E’s failure to provide comprehensive and accurate initial undergrounding project costs estimates and delays … created challenges for the city to forecast its future undergrounding cash flow,” consultants Bert Nuehring, Erik Nylund and Aaron Coen wrote.  

What the consultants found isn’t new. City Attorney Mara Elliott blasted SDG&E back in the spring of 2020 for overcharging the city to underground power lines. At the time, Elliott said that the utility refused to provide enough documentation to justify the soaring costs. So, the city stopped paying the company – in the middle of their contract negotiations for a new franchise agreement.  

San Diego is also still fighting SDG&E in court after the company refused to pay for the cost of moving some equipment so San Diego could build Pure Water, its billion-dollar wastewater recycling system. San Diego Superior Court Judge Eddie Sturgeon recently ruled in SDG&E’s favor. The city appealed the decision and it’s scheduled to be heard by the Fourth District Court of Appeal on June 11.  

Despite the undergrounding issues, the consultants ruled that SDG&E had met all their “significant” contract objectives.  

Anthony Wagner, an SDG&E spokesperson, said the company is “pleased the draft report ratified our strong franchise partnership with the city of San Diego.” 

“The audit results, which included 387 separate commitments or obligations made by SDG&E to the City, shows that we have met our audit objectives in all significant respects. We take pride in our work and will continue to improve internal processes as suggested by the auditor,” Wagner wrote.  

The city of San Diego signed a new 20-year contract with SDG&E back in 2021. The company, owned by Sempra, has been the city’s power provider for the past 100 years. The contract, called the franchise agreement, gives the company monopoly rights to build and maintain the power grid on public land. Franchise agreements were fairly cut and dry contracts in decades past. But as the city set new goals for combating climate change, and as energy costs have been steadily rising, the city used it to ask for more things from SDG&E. 

That includes an $80 million fee just to win the contract, which is supposed to come from the pockets of shareholders and shouldn’t be charged to customers. The new contract also set up this citizen-led Franchise Review Compliance Committee and SDG&E agreed to be audited every two years. Another new piece of the city’s franchise contract: The City Council has the option to cancel the contract after 10 years if it’s unsatisfied with SDG&E’s service.  

The committee’s own draft report of its work, set for discussion at its June 3 meeting, says that it’s too early to decide whether to recommend San Diego sever its ties with the company.  

“(The committee) recommends the City Council continue to closely monitor SDG&E’s compliance with the numerous provisions of the franchise agreement,” the committee wrote.  

The committee also recommended the City Council and mayor actually fill all the seats on the committee in the future. The committee should have five members, three selected by City Council and two by the mayor. One of the City Council’s appointees is currently vacant.   

SDG&E isn’t the only one with homework following the audit. The auditors knocked the city for failing to get its new Energy Cooperation Agreement with SDG&E signed under its own 90-day deadline. Instead, it took an extra six months to do. That agreement is where SDG&E agreed to a laundry list of commitments like planting thousands of additional trees in the city, building out infrastructure to support electric vehicles and committing up to $1 million in shareholder funds for 10 years toward a nonprofit that puts solar panels on low-income households. (To pay for all the other stuff, the agreement says SDG&E may raise rates.)   

The reason why it took so long? The city was busy negotiating with SDG&E on another agreement – called the administrative memorandum of understanding – that dictates how the company is allowed to function on city-owned rights of way where it builds the power grid.  

SDG&E was supposed to create a “work portal” to share information about all its projects with the city, but that didn’t happen, or when it did, it didn’t always have accurate information. That’s something the two parties appear to be working out, however, according to the consultants.  

The city declined to comment on these reports because they’re still in draft form, wrote Leslie Wolf Branscomb, a spokesperson for the city. 

Join the Conversation

7 Comments

  1. Thank you for raising awareness about this. Yet another reason to despise SDGE’s relationship with the city.

  2. SDGE is a usorious monopoly that sends biIlions to investors that incur zero risk for the overages, deferred maintenance, and system defects. They design a grid to maximize long distance transmission fees, and limit inside the distribution grid improvement to accommodate solar, batteries, and microgŕids. When I asked them why my 200 Amp panel was frying, per an electrician, they answered there were a lot of solar systems in the neighborhood and ” these old circuits just can’t handle the load. So they send the power back”. This while they send > 1 million a day in profit from San Diego alone. Am I tired of paying double the average rate in California, and triple the national rate while they maintain the same profit margin and continue raising rates 10% per year? YES!

  3. Does anyone in this city trust SDG&E besides its executives, board members, and shareholders? A for-profit monopoly will never put the consumer first. For its 2023 fiscal year, SEMPRA ENERGY, listed the following CEO pay ratio data on its annual proxy statement to the SEC. Jeffrey W. Martin CEO Pay-$27,448,194, Median Employee pay-$150,500, CEO Pay ratio-182:1.

    1. No, but I also don’t trust the city mayor and council either. 400 miles since 1970?! 7.5 miles a year, the bike lanes are growing faster. Estimated completion is year 2160 at this rate. With Elo-Rivera questioning the expenditure, it’s obvious they would like to take this, the water and road aspects and balance their budget while buying bad real estate around town. Have to deal with SDG&E later and the city misfits now.

  4. Gloria and Elo Rivera, the Council President, didn’t hold SDG&E’s feet to the fire when negotiating a new franchise agreement and once again we get the highest rates in the country. Gloria and Elo Rivera’s answer to all this is we need more money by raising the sales tax.

  5. Anyone who has had to work with this City or State government knows exactly why the costs are so high. Red tape is expensive!

Leave a comment
We expect all commenters to be constructive and civil. We reserve the right to delete comments without explanation. You are welcome to flag comments to us. You are welcome to submit an opinion piece for our editors to review.

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.