Ponds of untreated sewage at Punta Bandera
Ponds of sewage from Tijuana sit untreated at the Punta Bandera wastewater treatment plant, which has been out of operation for years. / File photo by Adriana Heldiz

The Mexican military is taking over reconstruction of a broken wastewater treatment plant in Tijuana that pollutes southern San Diego beaches in summertime. 

It’s the latest infrastructure project Mexican President Andrés Manuel López Obrador is entrusting to the military to complete, like Tren Maya, a new massive railway looping the Yucatan peninsula and a new airport in Mexico City. Now that list of projects includes Punta Bandera, a Tijuana wastewater plant that has been broken since at least 2014, which spews untreated sewage into the Pacific Ocean just six miles south of the U.S. border.  

Fixing Punta Bandera, also known as San Antonio de los Buenos, is a growing priority in the decades-long Tijuana River sewage crisis. Recent research by Scripps Institution of Oceanography linked the sewage pouring from that plant to swimmer illnesses during the summer in Imperial Beach, San Diego’s southernmost coastal city.   

The governor of Baja California, Marina Del Pilar Ávila, stands next to Ken Salazar, the U.S. Ambassador to Mexico, at the Punta Bandera wastewater treatment plant rehabilitation groundbreaking ceremony on Jan. 11 2024. / Courtesy of Vicente Calderon
The governor of Baja California, Marina Del Pilar Ávila, stands next to Ken Salazar, the U.S. Ambassador to Mexico, at the Punta Bandera wastewater treatment plant rehabilitation groundbreaking ceremony on Jan. 11 2024. / Courtesy of Vicente Calderon

“That plant if and when fixed … would eliminate 100 percent of our beach closures during the summer months,” said Imperial Beach Mayor Paloma Aguirre during a Dec. 1 forum held by the local League of Women Voters.  

The military takeover is welcome news to the governor of Baja California, Marina Del Pilar Ávila, who announced last month that SEDENA, the Secretary of National Defense, would take over the project.  

“The president told us not to worry, we put it in the hands of our friends, SEDENA, which has done extraordinary things throughout the country and this plant will be no exception,” Pilar Ávila said at a Dec. 27 press conference.  

Shovels at a groundbreaking at Punta Bandera, a wastewater treatment plant being rehabilitated by the Mexican Military, on Jan. 11 2024. / Courtesy of Vicente Calderon
Shovels at a groundbreaking at Punta Bandera, a wastewater treatment plant being rehabilitated by the Mexican Military, on Jan. 11 2024. / Courtesy of Vicente Calderon

Mexico pledged $144 million in 2022 under a treaty with the U.S. to fix a bunch of its broken wastewater infrastructure including Punta Bandera. The plant, which sits atop a mesa next to the coastline, is basically three giant ponds full of old wastewater that regularly flush into the Pacific Ocean. Victor Manuel Barragan, Pilar Ávila’s secretary of water, recently said the state was already working to dry out those lagoons.  

The leader of the U.S. International Boundary and Water Commission, Maria Elena Giner, during that same forum, signaled the military takeover was “good news” in that it meant a more secure source of funding to rehabilitate the plant. But 2024 is a presidential election year. López Obrador has termed out of the office he assumed in 2018. Whoever takes his place in the June election could reshuffle all of his priorities.  

Giner said she was told it would still take about two years for the military to build the plant. But Fernando Aguado, a SEDENA engineer, on Thursday committed to having it done by September of this year. 

The military takeover is the latest in a series of attempts to rectify Punta Bandera. Plans for a private Israeli company to partner with the Mexican government to rebuild the plant languished for years.  The company, Odis Asversa, wanted to recycle that wastewater into irrigation for Baja California’s famous but thirsty vineyards in Valle de Guadalupe.  

A sign outside the Punta Bandera wastewater treatment plant in Baja California announces the military takeover of its rehabilitation on Jan. 11, 2024. / Courtesy of Vicente Calderon
A sign near a highway in Tijuana announcing a double-decker highway project the military will undertake on Jan. 11, 2024. / Courtesy of Vicente Calderon

Fabian Yañez, a spokesman for the Israeli water company, told Voice of San Diego in 2021 that the company planned to pay the Mexican government for the sewage, treat it and sell it to grape growers for a profit. But the company struggled to get farmers to agree on a price for that water, which they otherwise pump from groundwater wells or purchase cheaply.  

Francisco “Kiko” Vega, Baja California’s governor from 2013 to 2019, signed the initial contract with Odis Asversa to sell treated wastewater. The next governor, Jaime Bonilla, announced in 2021 that his administration got approval for funding to fix the plant. Then Pilar Ávila, who used the Punta Bandera sewage spilling into the ocean as a backdrop for her gubernatorial campaign, promised clean beaches.  

Pipe from Punta Bandera
Untreated Tijuana sewage spills from this pipe into the Pacific Ocean on the Mexican coastline. / Photo by MacKenzie Elmer

It’s still unclear if recycling wastewater would be part of the military-built plant. But Baja California’s cities could certainly use it. The drought-stricken Colorado River is Tijuana’s only drinking water source. Wells are drying up further south toward Ensenada. And many Baja Californians experienced water shutoffs at some point during the debilitating drought of the past few years.  

Since Tuesday, about 60 percent of Tijuana’s 1,000 neighborhoods had their water shut off while workers make repairs to another leak in the Florido-Aguaje aqueduct which distributes drinking water from the Colorado River to 60 percent of the city. Tijuana had to buy expensive emergency water from California when that aqueduct sprung a leak last January.  

The U.S. Ambassador to Mexico, Ken Salazar, joined a groundbreaking ceremony at the Punta Bandera rehabilitation Thursday with Governor Pilar Ávila and Mayor Aguirre. He said solutions to the Tijuana River crisis can’t be solved on the U.S. side alone, referring to another broken and underfunded wastewater treatment border plant in San Diego that President Joe Biden has targeted in his budget requests.  

Join the Conversation

14 Comments

  1. Great reporting! It will be great if they can get this fixed.
    Does anyone know which water agency they purchase from during their emergency? And what they paid?

  2. 150$ Hr USD. That is Google online jobs, these jobs are one of the best ways as they offer several mind-blowing opportunities to make cash. qp And who doesn’t want to collaborate with a great brand like Google?
    Here Go………. https://JobsMakeCash.blogspot.com

Leave a comment
We expect all commenters to be constructive and civil. We reserve the right to delete comments without explanation. You are welcome to flag comments to us. You are welcome to submit an opinion piece for our editors to review.

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.